? Schedule Variance (SV%)

Calculate if your project is ahead or behind schedule as a percentage of planned work.

$
Current value of work actually performed
$
Value of work planned to be done by now

Schedule Variance (SV%)

0%

Understanding Schedule Variance

What is Schedule Variance?

Schedule Variance (SV) measures whether a project is ahead or behind schedule in dollar terms. Part of Earned Value Management (EVM).

  • SV > 0: Ahead of schedule
  • SV = 0: On schedule
  • SV < 0: Behind schedule

The Formula

Schedule Variance
SV = Earned Value (EV) - Planned Value (PV)

Worked Example

Scenario: Planned $100K work by today, completed $85K worth.
Step 1: EV = $85,000, PV = $100,000
Step 2: SV = $85,000 - $100,000 = -$15,000
SV = -$15,000 (behind schedule)

Pro Tips

  • Use with SPI: SV in $ + SPI as ratio gives full picture
  • Early action: Negative SV rarely improves on its own
  • Track weekly: Catch schedule slips early

Schedule Variance in Earned Value Management

Schedule Variance (SV) measures project timeline performance by comparing earned value to planned value. Unlike simple deadline tracking, SV provides a monetary view of schedule performance, enabling comparison across projects of different sizes.

Interpreting Schedule Variance

  • SV > 0 (Positive): Ahead of schedule. More value earned than planned by this date.
  • SV = 0: Exactly on schedule. Planned and actual progress align perfectly.
  • SV < 0 (Negative): Behind schedule. Less work completed than planned.

SV Limitations and Best Practices

Schedule Variance has a known limitation: it always converges to zero at project end, regardless of how late the project finishes. For this reason, experienced project managers use SV alongside percent complete metrics and critical path analysis. The Schedule Performance Index (SPI) provides a ratio view that's often more intuitive for stakeholders.

Pro tip: Track SV weekly, visualize trends, and investigate root causes when SV drops below -5%.

Frequently Asked Questions

How do you interpret schedule variance (SV) in project tracking?

Schedule Variance = Earned Value - Planned Value. Positive SV means ahead of schedule.

How do I interpret schedule variance?

SV > 0: Ahead. SV = 0: On schedule. SV < 0: Behind schedule.

What is the relationship between SV and SPI?

SPI = EV / PV gives efficiency ratio. SV gives absolute variance.

🔍 Authoritative References

For more information about professional and project management calculations, consult these trusted sources: